St Ives Town Deal has announced how the final stages of the project to redesign The Terrace junction, in St Ives, will proceed.

Terrace junction map

Surfacing will be carried out by Cormac on Sunday, 8th December, Monday, 9th December, and Tuesday, 10th December, between 7pm and 11pm each night. They are planning to complete the resurfacing in these three sessions, but may need to continue on Wednesday 11th December.

The imprint paving will be installed on the nights of 10th-12th, again with the possibility of a fourth night on the Friday if necessary. If all goes as scheduled the project will be completed on Friday 13th December.

The road will be closed to vehicles each night from 7pm until 11pm. Diversions will be in place at appropriate junctions around the town and at each arm of the closure.

Pedestrian access will still be available as the footways are not being surfaced. However, as heavy plant will be in operation behind the barriers, people are advised to take care. Access will be provided for emergency vehicles.

As these are noisy operations, people living in close vicinity to the works area may experience some short-term disruption, say the town deal team. There will be a generator in operation throughout each night, but the team will be using acoustic barriers to help mitigate the noise and will do their best to keep disturbance to a minimum.